by ramu65 » Mon Mar 17, 2014 5:01 pm
Hi Blackthorn...
Thanks a lot for your suggestions.I created an application scheduled to run every 5 minutes starting from 3.40 to 3.55.I added this application to long term plan using 2.2.2 option and then extended the current plan.But all the 4 occurrences started and executed at 3.40 itself.While creating the run cycle,I gave the input time as 3.40 and deadline time as 3.55.Are all the occurrences starting at 3.40 since I gave the input time as 3.40???....how can I resolve the problem???...In QCP,the input arrival time of each of the occurrences are displayed as 3.40,3.45,3.50 and 3.55 respectively.But in the "started at" column,all the occurrences are starting at 3.40...