Looked through the CA-7 Manuals and cannot find a report that will list jobs in the databaset that have a Submit time. I can't believe a report like this is unavailable, so I'm asking here. Has anyone found a way to list only jobs in the database that have a Submit time associated with them?
Second question, also about Reporting... we had a need to forecast jobs that use Tape Drives. The results from the FQTAPE command were not correct at all, does anyone know where CA-7 gets this information? Is this a parameter that would be updated by us first, then CA-7 can perform reporting on the number of tape drives needed etc?
Would WLB help in this situation?
Thanks for any help you can give me.