Could any please clarify how an DEADLINE time is defined in for a job in CA-7.
is there any logic behind defining the DEADLINE time...??
Thanks in advance..!!
With Regards,
Avinash Talamanchi.
deadline start time. See start time.
start time. Deadline start time. The time when a job should start in order for it to be finished by its due-out time. CA-7 calculates this by subtracting the job's lead time from its due-out time.