Let Main Job = A
Let Internal Job = B
LQ, JOB=A
A REQ 0276 302/1808 302/1800 302/1820 ALL- 065 SSCN 001 LATE
------------------------- REQUIREMENTS STATUS -------------------------
_______ INTERNAL JOB=/B DATE/TIME=07302/1600
Main job came into Queue at 1800 hrs.
#########################################################################
Internal job B last ran and completed at 1803 with entry mode as RUN
C 07302/1803 J B 0326 001 COMP RUN 0000 07302/1737 07302/1803
##########################################################################
If we see for details for job A in DB.3.2 we see as below
------------------------ CA-7 CPU JOB PREDECESSORS -------------------------
FUNCTION: LIST (FORMAT,LIST,UPD) PAGE 0001
PRED FOR JOB: A LIST-SCHID:
OPT SCHID LEADTM PRED-JOB NEXT-RUN
0 0000 /B YES
That is Job B has look back time of 0 hrs or job A has Lead time of 0 hrs
As per Defination for 0 hrs lead time -The Main job will not look back for the completion of its internal job; Main job should see the completion of its internal job. Which was true for our case.
###########################################################################
The problem is Main Job A did not get posted Even if Internal job B completed after job A came into queue. Please help me in with a logical reason as to why the job A was not posted even after successful completion of job B ?