by swati30j » Tue Mar 05, 2013 3:09 pm
Job A is a request job which is scheduled to run on weekends in ESP Schedular .
Start time of job A is based on the completion of its predecessor job and if it does not complete before 4.55CST.
We manually terminate it at 4.55 CST because prod region go live on 5.30CST
Please let us know the possible solutions for it so that we don't require to manually terminate it in case it crosses 4.55CT.
Any suggestions would be highly appreciated.
-
swati30j
-
- Posts: 1
- Joined: Fri Mar 01, 2013 7:04 pm
- Has thanked: 0 time
- Been thanked: 0 time
by enrico-sorichetti » Tue Mar 05, 2013 3:19 pm
a moderator please lock/delete this topic ...
it is a dangerous clone of
http://ibmmainframes.com/about60465.html hint ...
schedule a job at 5.00 to issue an unconditional cancel , if the job to be canceled is not there nobody will care
cheers
enrico
When I tell somebody to RTFM or STFW I usually have the page open in another tab/window of my browser,
so that I am sure that the information requested can be reached with a very small effort
-
enrico-sorichetti
- Global moderator
-
- Posts: 3006
- Joined: Fri Apr 18, 2008 11:25 pm
- Has thanked: 0 time
- Been thanked: 165 times
Return to All Other Tools